Vumatel is currently experiencing the following issue: 

 

Start Date & Time: 08/07/2026 @ 20:45

Affected Area/s: Protea Glen Phase 2-5  

Impact: Customers may experience no connectivity. 

 

Vumatel technicians are currently investigating. There is no ETR at the moment. 

 

Vumatel confirmed that this outage was resolved on 13/07/2026 @ 19:43. Please restart your devices and contact our Support Team should you still experience connection issues. 

 

Update (13/07/2026 @ 17:50):

 Technicians are still onsite busy with repairs.  

 

Update (13/07/2026 @ 16:32):

 Technicians are still onsite attending to fallouts, next update 18:00 

 

Update (13/07/2026 @ 08:55):

Vumatel technicians are on site to resume with the fault of cases nest update 14:00  

 

Update (12/07/2026 @ 19:49):

 Repairs on hold due to safety reasons  

 

Update (12/07/2026 @ 17:14):

Vumatel teams are still attending to the links that remain down. Next update: 20h00.  

 

Update (12/07/2026 @ 12:18):

Vumatel teams are still attending to the links that remain down. Next update: 17h00.  

 

Update (12/07/2026 @ 08:26):

Vumatel technicians are back on site this morning working on the services that remain down. Next update will be provided at 12h00.  

 

Update (11/07/2026 @ 19:14):

 Vumatel team will attend the remaining fallouts tomorrow morning  

 

Update (11/07/2026 @ 17:11):

Vumatel teams are still working on the services that remain down. Next update will be provided at 20h00.  

 

Update (11/07/2026 @ 15:04):

Vumatel teams are still working on the services that remain down. Next update will be provided at 17h00.  

 

Update (11/07/2026 @ 11:34):

Vumatel Teams are still working on the services that remain down. Next update will be provided at 14h00.  

 

Update (11/07/2026 @ 08:21):

Vumatel Teams will continue working on the services that remain down this morning. Next update will be provided at 11h00.  

 

Update (10/07/2026 @ 21:10):

Vumatel Team will attend the remaining fallouts tomorrow morning  

 

Update (10/07/2026 @ 17:18):

Technicians are actively attending to the remaining down cases. The next update will be provided at 20:00 pm  

 

Update (10/07/2026 @ 13:35):

Vumatel technicians are actively attending to the remaining down cases. The next update will be provided at 17h00.

 

Update (10/07/2026 @ 09:24):

 Vumatel technicians are actively attending to the remaining fallout cases, next update will be provided at 13h00  

 

Update (10/07/2026 @ 00:50):

The incident has been placed on hold due to safety concerns. The team will continue in the morning with repairs.  

 

Update (09/07/2026 @ 23:37):

Side A 144F- Completed 
Side B 144F- Completed

Side C 144F- Completed
Side D 144F- Splicing T5

72F Side A - Splicing T3
72F Side B- Prepping
48F Side A - Splicing T2
48F Side B - Splicing T2  

 

Update (09/07/2026 @ 22:23):

Side A 144F - Splicing T12, Side B 144F - Splicing T10, Side C 144F - Splicing T8, Side D 144F - Splicing T6 , Side A 72F - Splicing T3, Side B 48F - Splicing T2  

 

Update (09/07/2026 @ 21:22):

Side A - Splicing T11 Side B - Splicing T8 Side C - Splicing T6 Side D - Splicing T3  

 

Update (09/07/2026 @ 20:46):

Side A - Splicing T9 Side B - Splicing T8 Side C - Splicing T6 Side D - Splicing T2  

 

Update (09/07/2026 @ 16:35):

Side A - Splicing Tube 2 - Dome joint 1 Side B - Technicians are preparing the joints for splicing  

 

Update (09/07/2026 @ 17:30):

Side A - Splicing dome joint 1 Side B - Technicians are preparing the joints for splicing  

 

Update (09/07/2026 @ 16:31)

Side A - Technicians are preparing the joints for splicing Side B - Technicians are preparing the joints for splicing  

 

Update (09/07/2026 @ 15:29)

Side A- Technicians are preparing the joints for splicing Side B - Techs are stringing the cable  

 

Update (09/07/2026 @ 14:23):

Vumatel technicians are preparing the joints for splicing.

 

Update (09/07/2026 @ 13:15):

Vumatel technicians are pulling slack.

 

Update (09/07/2026 @ 12:18):

Vumatel civil team has arrived with stock and work has commenced.

 

Update (09/07/2026 @ 11:32):

Vumatel technicians are enroute to site with required stock.

 

Update (09/07/2026 @ 10:11):

Vumatel technicians are enroute to collect stock  

 

Update (09/07/2026 @ 09:48):

Vumatel technicians are busy auditing the cables.  

 

Update (09/07/2026 @ 08:24):

Vumatel technicians are on site investigating.  

 

Update (09/07/2026 @ 07:51):

Vumatel technicians are currently en route to site to further investigate the extent of the damages  

 

#ProteaGlenPhase2-5 #Vumatel #Outage 