Print
In an effort to improve stability on their legacy Vuma Villages network (previously known as SADV), Vumatel have, together with their backhaul fibre provider, identified a few critical sites where they have to conduct network remediation.
This means that Vumatel technicians will perform maintenance in the affected areas in Gauteng throughout December 2022.
Start Date: 12/12/2022
End Date: 29/12/2022
Impact: Customers on the Vuma Village network will experience slow/intermittent/no connectivity during parts of the maintenance period.
Please refer to the list of affected areas and their associated planned maintenance/upgrade dates below.
Area: JHB CBD/Merchandise
Associated planned upgrade dates:
12/12/2022
14/12/2022
15/12/2022
20/12/2022
21/12/2022
22/12/2022
28/12/2022
29/12/2022
Area: Senderwood
Associated planned upgrade dates:
11/12/2022
19/12/2022
21/12/2022
Area: Marlboro/Zinto's
Associated planned upgrade dates:
12/12/2022
14/12/2022
15/12/2022
18/12/2022
22/12/2022
29/12/2022
Area: Teraco Isando
Associated planned upgrade dates:
18/12/2022
21/12/2022
28/12/2022
Area: Sandton
Associated planned upgrade dates:
13/12/2022
20/12/2022
28/12/2022
Area: Ravenswood
Associated planned upgrade dates:
12/12/2022
14/12/2022
Area: Westbury
Associated planned upgrade dates:
15/12/2022
18/12/2022
19/12/2022
Area: Germiston
Associated planned upgrade dates:
19/12/2022
20/12/2022
29/12/2022
Area: Randburg/Randburg Motorcity
Associated planned upgrade dates:
11/12/2022
13/12/2022
Area: Wadeville
Associated planned upgrade dates:
11/12/2022
27/12/2022
Area: Fourways
Associated planned upgrade dates:
11/12/2022
18/12/2022
Area: Springs
Associated planned upgrade date/s:
13/12/2022
Area: Rynfields
Associated planned upgrade date/s:
15/12/2022
Area: Alrode
Associated planned upgrade date/s:
28/12/2022
Area: Krugersdorp
Associated planned upgrade date/s:
13/12/2022
Area: Mayo Clinic/Honeydew
Associated planned upgrade date/s:
19/12/2022
Area: Orlando Soweto
Associated planned upgrade date/s:
20/12/2022
Area: Rosebank
Associated planned upgrade date/s:
27/12/2022
Area: Turfontien Callistos
Associated planned upgrade date/s:
29/12/2022
We appreciate your patience and understanding throughout this upgrade period. Wishing you a happy and safe Festive Season.
#VumaVillages #Gauteng #Maintenance