Vumatel has scheduled the following planned maintenance:

 

Start Date & Time: 14/07/2025 08:00

End Date & Time: 18/07/2025 14:00

Duration: 5 Days

Affected Area/s: Roodepan Zone 1; Roodepan Zone 2 

 

Impact: Customers may experience no connectivity at some point during maintenance.

 

Update (18/07/2025 @ 14:15):

 We need to replace the 4km feeder cable and resplice all the fibres according to the splice diagram and cut out 7 splices through dome joints in the run to reduce the high losses . More updates to follow.

 

Update (18/07/2025 @ 13:24):

 We need to replace the 4km feeder cable and resplice all the fibres according to the splice diagram and cut out 7 splices through dome joints in the run to reduce the high losses.. More updates to follow.

 

Update (18/07/2025 @ 09:34):

 Services are connected with high losses, which may contribute to degraded performance.

Scope of Work:
We need to replace the 4km feeder cable and resplice all the fibres according to the splice diagram and cut out 7 splices through dome joints in the run to reduce the high losses.  

 