Vumatel is currently experiencing the following issue:  

 

Start Date & Time:04/04/2026 @ 09:09

Affected Area/s: Jabulani Phase 1

Impact: Customers may experience no connectivity. 

 

Vumatel technicians are currently investigating. There is no ETR at the moment. 

 

Update (06/04/2026 @ 10:13):

Vumatel confirmed that this outage was resolved on 06/04/2026 @ 10:13. Please restart your devices and contact our Support Team at 010 593 2665 or support@coolideas.co.za should you still experience connection issues.

 

Update (06/04/2026 @ 08:22):

Vumatel  Technicians are attending to the services that remain down  

 

Update (05/04/2026 @ 20:02):

 The incident has been placed on hold. The team will continue in the morning with repairs.  

 

Update (05/04/2026 @ 18:20):

 Technicians are still attending to the services that remain down Next update 9PM.

 

Update (05/04/2026 @ 15:07):

 Technicians are still attending to the services that remain down
Next update 6PM  

 

Update (05/04/2026 @ 10:13):

Technicians are on site busy with repairs 
Team 1 - Splicing T8 Team 2 - Splicing completed.  

 

Update (04/04/2026 @ 20:04):

The incident has been placed on hold. The team will continue in the morning with repairs  

 

Update (04/04/2026 @ 15:47):

Vumatel technicians are busy splicing.  

 

Update (04/04/2026 @ 13:42):

 Awaiting the civil team to arrive with stock.  

 

Update (04/04/2026 @ 13:42):  

 Stock en-route and team is completing to prep.  

 

Update (04/04/2026 @ 12:39):  

 Technicians are enroute to collect stock  

 