Vumatel is currently experiencing the following issue:
Start Date & Time: 04/04/2026 @08:05
Affected Area/s: Dlamini
Impact: Customers may experience no connectivity.
Vumatel technicians are currently investigating. There is no ETR at the moment.
Update (07/04/2026 @ 16:29):
Vumatel confirmed that this outage was resolved on 07/04/2026 @ 16:29. Please restart your devices and contact our Support Team at 010 593 2665 or support@coolideas.co.za should you still experience connection issues.
Update (07/04/2026 @13:14):
Vumatel technicians are attending to the remaining down services. Next update will be provided at 16:00.
Update (07/04/2026 @ 10:19):
Vumatel technicians are attending to the remaining down services. Next update will be provided at 13:00.
Update (07/04/2026 @ 08:08):
Technicians are attending to the remaining down services. Next update will be provided at 10:00.
Update (06/04/2026 @ 19:52):
Vumatel Technicians are attending to the remaining down services. Next update will be provided at 10:00.
Update (06/04/2026 @ 19:52):
Repairs on hold due to safety reasons, teams will resume tomorrow morning
Update (06/04/2026 @ 18:37):
Vumatel Technicians are still attending to the services that remain down Next Update: 06/04/2026 20h00
Update (06/04/2026 @ 15:39):
Vumatel Technicians are still attending to the services that remain down Next Update: 06/04/2026 18h00
Update (06/04/2026 @ 12:07):
Technicians are still attending to the services that remain down
Next Update: 06/04/2026 15:00
Update (06/04/2026 @ 09:19):
Vumatel technicians are still attending to the services that remain down
Next Update: 06/04/2026 12:00
Update (05/04/2026 @ 08:21):
Technicians are attending to the services that remain down.
Update (05/04/2026 @ 17:33):
Splicing in progress
Side B
Team 1- Completed
Team 2- Splicing T9
Update (05/04/2026 @ 15:49):
Repairs are still in progress:
Team 1- Completed
Team 2 - splicing T5
Update (05/04/2026 @ 14:46):
Side A – Team 1 splicing complete; Team 2 on Tray 11.
Side B – Team 1 splicing complete; Team 2 on Tray 1.
Update (05/04/2026 @ 12:07):
Dlamini,Moroka
Team 1- Completed
Team 2 - Splicing T9
Side B
Team 1- Splicing T3
Team 2- Splicing T1
Update (05/04/2026 @ 02:38):
Incidents on hold, teams will continue around 8 am
Update (05/04/2026 @ 01:20):
Splicing in progress: Team 1- Splicing T10
Team 2- Splicing T6
Update (04/04/2026 @ 23:59):
Splicing in progress Team 1- Splicing T4 Team 2- Splicing T2
Update (04/04/2026 @ 21:28):
Splicing in progress
Team 1- Splicing T4
Team 2- Splicing T2
Update (04/04/2026 @ 20:46):
Splicing in progress
Team 1- Splicing T1
Team 2- Sizing fibres
Update (04/04/2026 @ 18:46):
Prepping is almost done
Update (04/04/2026 @ 17:42):
Vumatel technicians are still preparing the joints for splicing
Update (04/04/2026 @ 15:49):
Vumatel technicians are on site: Prepping in progress
Update (04/04/2026 @ 14:37):
Civil team has arrived and work has commenced.
Update (04/04/2026 @ 13:39):
Vumatel Technicians are en-route to site with collected stock.
Update (04/04/2026 @ 11:36):
Vumatel Technicians are enroute to collect stock .
Update (04/04/2026 @ 11:36):
Vumatel Technicians are on site localising the fault.
#Dlamini #Vumatel #Outage