Vumatel has scheduled the following planned maintenance: 

 

Start Date & Time: 14/08/2026 @ 23:30

End Date & Time: 15/08/2026 @ 07:30

Duration: 8 hours

Affected Area/s: Witbank 

 

Impact: Customers may experience no connectivity at some point during maintenance. 

 

Update (15/08/2026 @ 11:09):

client paid for her connection on Thursday 

 

CFA11-13-0053 DFA Witbank Aggr_Retail_City Teraco Isando JB1 (Active) 

 

DFA confirmed services cannot be re-routed. 
Witbank / Emalahleni Ackerville will drop 
Firmware upgrades on the Core equipment at Teraco Isando 

 

Change Description and Motivation: 
The DFA APS team need to perform firmware upgrades on the Core equipment at Teraco Isando, to keep the nodes with updated firmware as per vendor recommendations. 

 

 