Vumatel has scheduled the following planned maintenance:
Start Date & Time: 14/08/2026 @ 23:30
End Date & Time: 15/08/2026 @ 07:30
Duration: 8 hours
Affected Area/s: Witbank
Impact: Customers may experience no connectivity at some point during maintenance.
Update (15/08/2026 @ 11:09):
client paid for her connection on Thursday
CFA11-13-0053 DFA Witbank Aggr_Retail_City Teraco Isando JB1 (Active)
DFA confirmed services cannot be re-routed.
Witbank / Emalahleni Ackerville will drop
Firmware upgrades on the Core equipment at Teraco Isando
Change Description and Motivation:
The DFA APS team need to perform firmware upgrades on the Core equipment at Teraco Isando, to keep the nodes with updated firmware as per vendor recommendations.
#Witbank #Vumatel #Maintenance