Bram Fischerville Ward 49, Bram Fischerville Ward 44 Phase 5 - INC-000008932

Support Portal  »  Fibre  »  Viewing Article

  Print

Vumatel is currently experiencing the following issue:

Start Date & Time: 16/04/2025 @ 10:01
Affected Area/s: Bram Fischerville Ward 49, Bram Fischerville Ward 44 Phase 5  
Impact: Customers may experience no connectivity.

Vumatel technicians are currently investigating. There is no ETR at the moment.

 

Update (19/04/2025 @14:48)

Technicians are still busy attending to the services that remain down  

 

Update (19/04/2025 @13:25)

Technicians are currently attending to the services that remain down  

 

Update (19/04/2025 @09:16)

Technicians are attending to the services that remain down  

 

Update (18/04/2025 @18:44)

 Repair on hold due to safety reasons, the team will attend the remaining cases tomorrow morning 

 

Update (18/04/2025 @17:10)

Technicians are making progress with the remaining cases and will complete work as soon as possible.  

 

Update (18/04/2025 @ 14:33)

Technicians are actively working on the remaining fallout cases, ensuring a thorough and efficient resolution. Further updates will be provided at 17:00  

 

Update (18/04/2025 @ 11:07)

Teams are still troubleshooting links testing down  

 

Update (18/04/2025 @ 08:34)

Technicians are attending to the services that remain down

 

Update (17/04/2025 @ 20:51)

The technicians have completed the required repairs and have indicated that they will resume work on the remaining fallout cases tomorrow morning.

 

16/04/2025 @ 19:17

Splicing last tube Last 12 fibers of 144
288 completed
72 completed  

 

16/04/2025 @ 18:04

 Splicing in progress Splicing in progress 288F completed 100% / completed 144F side A completed 144F side B 99%  

 

Update (17/04/2025 @ 16:58)

Splicing in progress side A 288F completed side B 98% completed 144F side A completed 144F side B 98%  

 

Update (17/04/2025 @ 15:51):

 Splicing in progress 144F 90% completed 288F 70% completed 72F completed  

 

Update: 17/04/2025 14:40

Splicing in progress 288F splicing 60% 144F 60% 72F completed  

 

Update: 17/04/2025 12:39

 Splicing in progress 72F 30% splicing completed 144 prepping 40% 288F 30% splicing completed  

 

Update: 17/04/2025 11:07

Technicians are preparing a 288F and 72F for splicing  

 

Update: 17/04/2025 10:51

Technicians are preparing 288F and 72F for splicing 144F also

 

Update: 17/04/2025 09:43

Technicians are onsite with stock stringing started

 

Update: 17/04/2025 09:11

Technicians are enroute to collect stock

 

Update: 17/04/2025 08:57

Technicians notified of possible outage


#BramFischervilleWard49 #BramFischervilleWard44Phase5 #VumatelReach #Outage