Vumatel has scheduled the following planned maintenance:
Start Date & Time: 30/03/2026 21:00
End Date & Time: 07/04/2026 18:00
Duration: 9 Days
Affected Area/s: Nora - Johannesburg
Impact: Customers may experience no connectivity at some point during maintenance.
Please note: Service migration from Zhone OLT to Huawei OLT at the POP and swapping out old Zhone ONTs with new Huawei ONTs at the client's premises
MDU's affected:
Eliana Court
LC9P3
LC9P4
LC9P5
LC9P6
Fibrehood ( Nora )
Update (31/03/2026 @19:54):
Vumatel confirmed 45 clients swapped today and 1 fallout case, moving another port tomorrow morning LC9P6
Update (31/03/2026 @07:02):
Vumatel teams going back to site this morning to continue with yesterday's list and moving another port today LC9P5
Update (30/03/2026 @17:53):
45 clients got swapped today, teams will continue tomorrow......
Update (30/03/2026 @10:20):
Vumatel teams onsite swapping already on LC9P3 and LC9/4