Vumatel has scheduled the following planned maintenance:
Start Date & Time: 01/09/2025 09:30
End Date & Time: 05/09/2025 14:00
Duration: 5 days
Affected Area/s: Highbury - Cape Town
Impact: Customers may experience no connectivity at some point during maintenance.
Update: 03/09/2025 09:08
Remaining down services are being attended to
Update: 02/09/2025 12:55
Teams are still busy splicing the panels.
Update: 01/09/2025 21:42
Techs done with Splicing going to patch all the clients back tomorrow
|
|
Update: 01/09/2025 15:09
Prep work has been done on both panels . Splicing will start.
Update: 01/09/2025 12:23
Teams have corrected the cores by the POP. They are now busy prepping the panel for splicing.
|
|
Update: 01/09/2025 09:24
Will be starting this change now.
#Highbury #Vumatel #Maintenance