Vumatel has scheduled the following emergency maintenance:
Start Date & Time: 03/07/2025 08:00
End Date & Time: 07/07/2025 17:00
Duration: 4 Days
Affected Area/s: Germiston Zone 3, Germiston Zone 4, Germiston Zone 5, Germiston Zone 6
Impact: Customers may experience no connectivity at some point during maintenance.
The team will be replacing the 144f cable to ensure optimal network performance and uptime.
Scope of work:
We will be eliminating 9 splice throughs on the 144f link cable from the pop side because we have high losses affecting clients, joint will be remediated as well.
Component/s Affected:
Zones:
Germiston Zone 3
Germiston Zone 4
Germiston Zone 5
Germiston Zone 6
#GermistonZone3,4,5&6#Vumatel #Maintenance