Vumatel has scheduled the following planned maintenance:
Start Date & Time: 30/03/2026 08:00
End Date & Time: 07/04/2026 17:00
Duration: 9 Days
Affected Area/s: Devonshire Park - Johannesburg
Impact: Customers may experience no connectivity at some point during maintenance.
Please note: Service migration from Zhone OLT to Huawei OLT at the POP and swapping out old Zhone ONTs with new Huawei ONTs at the client's premises
Affected Components:
Riverside
FDP-AG1
Update (01/04/2026 @09:28):
Team on site swapping clients on LC01P2
Update (31/03/2026 @14:11):
Teams are in the process of Swapping ONTs linked to LC1P1
Update (31/03/2026 @06:27):
Team will be starting the Swaps today of LC1P1 to LC1P0 on the Huawei
Update (30/03/2026 @20:06):
Team will Resume in the Morning
Update (30/03/2026 @11:45):
Please Note Swaps will start tomorrow 31/03/2026
Update (30/03/2026 @09:01):
Teams busy ensuring all software and scrips are loaded onto the OLTs to allow us to start the change
#DevonshirePark #Vumatel #Maintenance