Vumatel is currently experiencing the following issue:
Start Date & Time: 02/03/2025 @ 13:49
Affected Area/s: Birchleigh
Impact: Customers may experience no connectivity.
Vumatel technicians are currently investigating. There is no ETR at the moment..
Update (11/03/2025 08:52):
Vumatel confirmed that this outage was resolved on 09/03/2025 21:57. Please restart your devices and contact our Support Team at 010 593 2665 or support@coolideas.co.za should you still experience connection issues.
Update - 06/03/2025 17:14
|
The team is facing difficulties accessing certain clients who remain offline.
|
|
Update - 06/03/2025 13:40
Remaining down services are being attended to
Update - 06/03/2025 11:20
Techs to attend the remain cases
Update - 06/03/2025 09:55
Remaining down services are being attended to
Update - 05/03/2025 20:53
Repairs on hold due to adverse weather conditions
Update - 05/03/2025 16:40
Remaining down services are being attended to
Update - 05/03/2025 16:11
|
The team is currently splicing the last tube on the 144F link cable. Once completed, they will proceed with splicing the 24F RetractorNet.
|
|
Update - 05/03/2025 15:11
Four trays remain for splicing.
Update - 05/03/2025 12:37
Done splicing 288f, We now splicing 2nd tray of 144f link cable
Update - 05/03/2025 09:19
Splicing in progress on the remaining tubes
Update - 05/03/2025 07:29:
|
Team on route to site to continue with splicing on remaining tubes.
|
Update - 05/03/2025 @ 03:04:
|
Technicians are still busy with repairs
|
Update - 04/03/2025 @ 20:54:
|
Two tubes remain on Side A of the 288F, while Side B is three-quarters complete.
|
Update - 04/03/2025 17:02
|
The team is currently splicing all the way. Extra caution is required as they are working with the tricky dotted cables.
|
|
Update - 04/03/2025 13:10
Splicing in progress
Update - 04/03/2025 12:38
Splicing still in progress on the 288F.
Update - 04/03/2025 11:24
Progressive update requested, awaiting feedback from site
Update - 04/03/2025 10:21:
|
1x288F -50% splicing 2nd 1x288F- 10% splicing on either sides. Last 144F splicing-50% on side A 20% on side B
|
|
Update - 04/03/2025 09:32:
Splicing in progress - 1X288F
Update - 04/03/2025 08:05:
ANO will advise once a team is onsite
Update - 04/03/2025 07:37:
Progressive update requested, awaiting feedback from ANO.
Update (03/03/2025 @ 21:49):
Vumatel technicians are splicing the last core tube. There is still no ETR at the moment. More updates to follow.
Update (03/03/2025 @ 21:10):
Splicing is still in progress. There is still no ETR at the moment. More updates to follow.
Update (03/03/2025 @ 17:10):
Vumatel technicians are splicing more new cables. There is no ETR at the moment.. More updates to follow.
Update (03/03/2025 @ 15:39):
Vumatel technicians are done splicing parts of the new cables and are preparing for floating. There is still no ETR at the moment. More updates to follow.
Update (03/03/2025 @ 13:02):
Vumatel technicians are splicing the new cables. There is no ETR at the moment. More updates to follow.
Update (03/03/2025 @ 10:09):
Vumatel technicians are back on site localising the fault. There is no ETR at the moment. More updates to follow.
Update (02/03/2025 @ 18:45):
Vumatel technicians confirmed that repairs were placed on hold for safety reasons. There is no ETR at the moment. More updates to follow.
Update (02/03/2025 @ 14:24):
Vumatel technicians are on site localising the fault. There is no ETR at the moment. More updates to follow.
#Birchleigh #Vumatel #Outage