Vumatel is currently experiencing the following issue:
Start Date & Time: 01/11/2026 @03:07
Affected Area: Algoa Park
Impact: Customers may experience no connectivity.
Vumatel technicians are currently investigating. There is no ETR at the moment.
Update (01/11/2026 @ 16:38)
Vumatel confirmed that this outage was resolved on 01/11/2026 @ 16:38. Please restart your devices and contact our Support Team should you still experience connection issues.
Update (01/11/2026 @ 15:55)
Vumatel Technicians have completed repairs. OLT is stable.
Update (01/11/2026 @14:46)
Splicing in progress Civils: 95% Preparation: 100% Splicing: 90%
Update (01/11/2026 @13:15)
Splicing in progress Civils: 90% Preparation: 100% Splicing: 50%
Upate (01/11/2026 @12:06)
Technicians are preparing the joints for splicing Civils: 60% Preparation: 30% Splicing: 05%
Update (01/11/2026 @11:22)
Technicians are preparing the joints for splicing Civils: 60% Preparation: 30% Splicing: 05%
Update(01/11/2026 @10:04)
Slack recovery in progress. 288F
Update (01/11/2026 @09:17)
OLT restored, teams are now focusing on the Jarman feeder cable route.
Update (01/11/2026 @08:09)
Backhaul Cable Prepping at: 80% Side A Civils at: 75% Side B Civils at: 75%
Update (01/11/2026 @07:22)
Backhaul Cable Prepping at: 50% Side A Civils at: 50% Side B Civils at: 50%
Update (01/11/2026 @06:30)
Team on site and starting with civils.
Update (01/11/2026 @05:06)
| Civil team has arrived and work has commenced |
Update (01/11/2026 @03:25)
Technicians are on site localising the fault
Update (01/11/2026 @03:07)
Technicians on route to site
#AlgoaPark #Vumatel #Outage